Foster Dam Crane Demolition

CRANE REMOVAL AND DEMO

This project required the demolition of a concrete gantry crane atop Foster Dam in Sweet Home, Oregon. Features of work included aluminum, steel, and oil recycling, concrete demolition with chain, ring, and wall saws, slurry containment and design and installation of a new aluminum handrail system. Work was completed ahead of schedule in only 15 working days.

OWNER
US Army Corps of Engineers, Portland District
LOCATION
Linn County, Oregon
YEAR
2017